Equinix opens US$290m SG6 data centre in Singapore at 1.2 PUE
Equinix opened US$290 million SG6 in Singapore on November 6, targeting 1.2 PUE, 1,550 cabinets and 20MW IT load at full build-out, with a 2027 AI research hub and SG7 next.

Event log
- SG6 opened on November 6 at a cost of US$290 million.
- Full-load PUE target: about 1.2; phase one holds about 1,550 cabinets.
- IT load reaches 20 megawatts at full build-out.
- 17 of 31 subsea cables landing in Singapore terminate in Equinix facilities.
- Inference is expected to account for half of AI workloads by 2030.
What did Equinix open in Singapore?
Equinix opened its US$290 million SG6 data centre in Singapore on November 6 with a full-load power usage effectiveness (PUE) target of about 1.2, a figure more common in Scandinavia than near the equator.
Singapore offers data centre operators little natural advantage: there is no winter, no cool season and little spare land, and the government counts every watt.
Tan Kiat How, Senior Minister of State for the Ministry of Digital Development and Information, opened the facility. It is Equinix’s sixth Singapore data centre and the first the company built under the government’s Data Centre-Call for Application (DC-CFA) framework.
The framework releases scarce capacity only to operators that commit to hard efficiency targets. Phase one holds about 1,550 cabinets, with IT load set to rise to 20 megawatts at full build-out.
SG6 adds local compute capacity without relaxing the government’s power-efficiency requirement.
How does SG6 manage tropical heat?
Cooling is the biggest drag on PUE, so Equinix put its engineering effort there. SG6 uses magnetic-bearing chillers, which lose less energy to friction than conventional units.
The plant has headroom, so the chillers never run flat out even when the building reaches full occupancy. They use less energy cruising than at full throttle, and Singapore’s cooler nighttime air gives them a break.
In the data halls, Equinix’s patented cooling arrays sit alongside liquid cooling for dense graphics processing unit racks. This mix addresses a local operating environment with no winter, no cool season and little spare land.
Samson Jeremiah, who leads design delivery for Equinix in Asia-Pacific and has worked on SG6 since 2019, said: “You don’t get the benefit of free cooling anytime during the day.” He judged the 1.2 PUE remarkable under those conditions.
Roughly one megawatt-peak of solar sits on the roof and facade, including vertical solar panels that remain rare because neighbouring towers cast shadows. Jeremiah said the team remained in a learning phase and considered SG6 fortunate because its neighbours are low-rise.
Green strips on the facade were designed in-house. Their cooling effect will remain unknown until the plants cover the wall. The structure uses locally sourced, low-carbon concrete containing recycled ash in place of new material.
Rainwater supplies irrigation and cooling towers, while NEWater reduces reliance on potable water. Together, these measures target cooling demand and water consumption inside the same facility.
SG6 treats heat, land and water as core design constraints rather than later operating problems.
Where does the efficiency mandate reach tenants?
Equinix also requires customer servers to meet Singapore’s SS 715:2025 energy-efficiency standard. The standard requires equipment to run safely at temperatures up to 30°C, pushing the facility’s efficiency mandate beyond its walls and onto tenant hardware.
Tenant hardware now forms part of SG6’s efficiency equation.
Why is SG6 aimed at inference?
Yee May Leong, Equinix’s Singapore managing director, said: “Because we pushed the PUE to 1.2, we actually built the data centre to be AI-ready.” SG6 prioritised sustainability, and its liquid cooling and power density followed that design choice.
Equinix is not chasing the 100-megawatt training clusters appearing elsewhere. Leong said SG6 was not GPU-intensive. The company is instead betting on inference and interconnection.
Leong expects inference to make up half of AI workloads by 2030. She also cited Equinix’s local reach: 17 of the 31 subsea cables landing in Singapore terminate at its facilities, and the company counts more than 1,000 local customers.
Leong argued that AI agents never sleep, so inference for those agents must sit close to users, clouds and networks. This makes continuous local service more important than a single large training cluster.
CEO Adaire Fox-Martin, who attended the opening, framed AI as Equinix’s third inflection point after neutral network exchanges and hybrid cloud. She said running AI at scale with control and sovereignty creates challenges that compute alone cannot solve.
SG6 is an inference and interconnection platform built for continuous demand, not a hyperscale training campus.
What will Equinix test at SG6?
SG6 will host a co-innovation hub with the National University of Singapore’s Energy Solutions Hub. Due in 2027, it will test four areas:
- Direct-current power.
- AI-driven digital twins for cooling.
- Direct-to-chip cooling.
- The embedded water footprint of electricity.
Equinix has already signed AI customers for SG6. Leong would not name them, but said they comprised the group of AI users and providers that typically adopt such infrastructure.
The 2027 hub will test four power, cooling and water methods at SG6.
Where does expansion go next?
An SG7 data centre will rise on Singapore’s Jurong Island after Equinix received the second DC-CFA award in August. The project must use new green-energy pathways, including biomethane, ammonia or fuel cells.
Equinix has selected two pathways but has yet to decide which two. With SG6, the company now operates six Singapore data centres, all with 100 per cent renewable coverage since 2020.
Globally, Equinix runs more than 280 data centres, serves about 11,000 customers and operates across 36 countries.
For enterprise buyers, SG6 offers local inference capacity under strict efficiency rules; SG7 will test whether Equinix can repeat that performance with new energy pathways.
via techgoondu.com (Source)
More from Amara Osei
Show full bio
Correspondent covering regulation, policy and their impact on enterprise information technology and the leaders who run at CIO Monitor.
230 articles
The newsroom digest
One email a day with the stories that matter. No noise.
Cross-references
- Equinix Opens SG6 in Singapore at PUE 1.2 Under New Green Rules
- Thailand Unveils Seven-Tier Power Rules for Data Centres
- OpenAI renames data centers 'compute campuses' and pledges grid relief
- IEA: AI to drive 70% rise in data center emissions by 2030
- Mississippi Board Upholds Air Permit for SpaceX's 1.2 GW Power Plant